Walk any jobsite at seven in the morning and follow the cords. They come off a spider box, run under a door, across a slab, through a puddle that was not there yesterday, and end at a grinder that three different trades have borrowed this week.
Nobody owns that cord. The electrician hung the box, a laborer strung the first fifty feet, somebody's foreman added a second one, and the man using it right now has no idea who checked it last or whether anyone did. That is the gap 1926.404(b)(1) was written to close, and it closes it in a way most sites never quite commit to.
The rule does not ask you to be careful with temporary power. It makes you pick one of two programs and then actually run it. Temporary power spreads faster than anyone's plan for it. By the time a site looks like this, the cords have been added by four different trades. You pick one. You do not get to do neither.
The opening line of the standard is a fork in the road. The employer uses either ground-fault circuit interrupters as specified in (b)(1)(ii), or an assured equipment grounding conductor program as specified in (b)(1)(iii). The GFCI path covers all 120-volt, single-phase, 15- and 20-ampere receptacle outlets on construction sites which are not part of the permanent wiring of the building or structure and which are in use by employees.
Those outlets get approved ground-fault circuit interrupters for personnel protection. There is one narrow carve-out. Receptacles on a two-wire, single-phase portable or vehicle-mounted generator rated not more than 5kW do not need GFCI protection, but only where the circuit conductors of the generator are insulated from the generator frame and all other grounded surfaces. That is a specific machine wired a specific way, not a general pass for generators.
The assured grounding path is the other option, and it is the one people choose by accident. It covers all cord sets, receptacles which are not part of the building or structure, and equipment connected by cord and plug which are available for use or used by employees. Most sites end up here without deciding to, because somebody hung non-GFCI boxes and the cords multiplied.
If that is your site, you are on the assured grounding path whether or not anyone has written it down, and the standard has a long list of things that path requires. What the assured grounding path actually obligates you to This is the part that gets missed. It is not a philosophy, it is a schedule.
What has to happen What it covers How often Visual inspection for external defects such as deformed or missing pins or insulation damage, and for indications of possible internal damage Cord sets, attachment caps, plugs, cord-set receptacles, and equipment connected by cord and plug. Cord sets and receptacles that are fixed and not exposed to damage are excepted Before each day's use Continuity test.
All equipment grounding conductors shall be electrically continuous All equipment grounding conductors Before first use Correct attachment test for the equipment grounding conductor Each receptacle and attachment cap or plug Before first use Retest Equipment returned to service following any repairs Before it goes back in service Retest Equipment after any incident which can be reasonably suspected to have caused damage Before it is used again Periodic retest Cord sets, receptacles not part of the permanent wiring, and cord- and plug-connected equipment At intervals not to exceed 3 months Periodic retest Cord sets and receptacles that are fixed and not exposed to damage At intervals not exceeding 6 months Alongside that schedule, the standard wants three things that have nothing to do with testing: A written description of the program, including the specific procedures the employer adopted, available at the jobsite for inspection and copying by the Assistant Secretary and by any affected employee.
Available at the jobsite. Not in a binder at the office. One or more designated competent persons, as defined in 1926.32(f), to implement the program. Designated, not assumed. Records of the tests. The record identifies each receptacle, cord set and cord- and plug-connected equipment that passed, with the last date tested or the interval for which it was tested.
It can be kept by logs, color coding or other effective means, and it is maintained until a more current record replaces it. That last line is why the colored tape you see wrapped around cord ends is not decoration. Quarterly color coding is one of the accepted ways to keep the record, and it is the only one a foreman can verify from six feet away.
Where it falls apart in the field The standard is not hard. Running it across a site with twelve subcontractors is. Nobody is designated. The program exists in the safety manual and no named person implements it, so the three-month clock never starts. The daily visual inspection is treated as optional.
It is the one requirement in the whole paragraph that happens every single day, and it is the one that catches a damaged cord before it matters. Borrowed tools fall out of the system. A grinder that moves between three trades belongs to whoever's program tested it last, and often that is nobody's. Damaged equipment goes back in the gang box.
The rule is plain that equipment found damaged or defective shall not be used until repaired. In practice it gets set aside, then picked up by somebody who did not see it get set aside. The record cannot be produced. Testing happened. Nobody can show which items passed or when, which under the standard is the same as not having the record.
What a GC should ask for On a multi-employer site this is worth settling before the first cord gets strung, not during an inspection. Which path is this project on, GFCI or assured grounding, and is it the same answer for every trade? If it is assured grounding, who is the designated competent person, by name, for each employer? Where does the written description live on site?
What does the current quarter's color look like, and who applies it? What happens to a cord that fails, physically, so it cannot be picked back up? A site that answers those five quickly is running the program. A site that has to go find somebody is not. Frequently Asked Questions Does a GFCI in the cord end count?
The standard requires approved ground-fault circuit interrupters for personnel protection on the covered receptacle outlets. In-line and plug-in GFCI devices are commonly used to accomplish that, but the protection has to actually be in place and working for the outlets in use, not sitting in a job box. If we use GFCIs everywhere, do we still inspect cords?
The daily visual inspection sits inside the assured grounding paragraph, so it is not triggered by the GFCI path. That said, a damaged cord is still a hazard and still citable under other parts of Subpart K, and no competent super is going to let a cord with missing pins stay in service because of which paragraph it lives in. Can different subs on the same site use different paths?
Each employer has the obligation for its own employees and equipment. That is legal and it is also how sites get confused, which is why most GCs pick one answer and write it into the subcontract. Is color coding required? No. The requirement is a record that identifies what passed and when, kept by logs, color coding or other effective means.
Color coding is just the method that survives contact with a jobsite best. What does "fixed and not exposed to damage" mean? It is the narrow exception that stretches a cord set's periodic test from three months to six, and that exempts it from the daily visual. It describes something installed and protected, not a cord that happens to be lying in a corner this week.
Key Takeaways 1926.404(b)(1) makes you choose: GFCI protection, or an assured equipment grounding conductor program. There is no third option. The GFCI path covers 120-volt, single-phase, 15- and 20-ampere receptacles that are not part of the permanent wiring and are in use by employees. The generator carve-out is narrow: two-wire, single-phase, not more than 5kW, with conductors insulated from the frame and all other grounded surfaces.
The assured grounding path requires a daily visual inspection, two tests, retests after repair or a suspected damage incident, and periodic retests at 3 months, or 6 for fixed cord sets and receptacles not exposed to damage. It also requires a written description on site, designated competent persons, and a record of what passed and when. Equipment found damaged or defective is out of service until repaired.
Related reading Electrocution is now the top killer on powered access equipment If it's not inspected, it's not safe Our electrical safety material, if you want this in a form you can hand a crew. Sources 29 CFR 1926.404, Wiring design and protection (OSHA) 29 CFR 1926.32, Definitions (OSHA) TriCore Safety is a construction and industrial safety consulting firm founded by Chris Fredette, CHST.
We write temporary power and assured grounding programs and walk them in the field to see whether they match the work. Tell us about the job.
Walk any jobsite at seven in the morning and follow the cords. They come off a spider box, run under a door, across a slab, through a puddle that was not there yesterday, and end at a grinder that three different trades have borrowed this week.
Nobody owns that cord. The electrician hung the box, a laborer strung the first fifty feet, somebody's foreman added a second one, and the man using it right now has no idea who checked it last or whether anyone did. That is the gap 1926.404(b)(1) was written to close, and it closes it in a way most sites never quite commit to.
The rule does not ask you to be careful with temporary power. It makes you pick one of two programs and then actually run it. Temporary power spreads faster than anyone's plan for it. By the time a site looks like this, the cords have been added by four different trades. You pick one. You do not get to do neither.
The opening line of the standard is a fork in the road. The employer uses either ground-fault circuit interrupters as specified in (b)(1)(ii), or an assured equipment grounding conductor program as specified in (b)(1)(iii). The GFCI path covers all 120-volt, single-phase, 15- and 20-ampere receptacle outlets on construction sites which are not part of the permanent wiring of the building or structure and which are in use by employees.
Those outlets get approved ground-fault circuit interrupters for personnel protection. There is one narrow carve-out. Receptacles on a two-wire, single-phase portable or vehicle-mounted generator rated not more than 5kW do not need GFCI protection, but only where the circuit conductors of the generator are insulated from the generator frame and all other grounded surfaces. That is a specific machine wired a specific way, not a general pass for generators.
The assured grounding path is the other option, and it is the one people choose by accident. It covers all cord sets, receptacles which are not part of the building or structure, and equipment connected by cord and plug which are available for use or used by employees. Most sites end up here without deciding to, because somebody hung non-GFCI boxes and the cords multiplied.
If that is your site, you are on the assured grounding path whether or not anyone has written it down, and the standard has a long list of things that path requires. What the assured grounding path actually obligates you to This is the part that gets missed. It is not a philosophy, it is a schedule.
What has to happen What it covers How often Visual inspection for external defects such as deformed or missing pins or insulation damage, and for indications of possible internal damage Cord sets, attachment caps, plugs, cord-set receptacles, and equipment connected by cord and plug. Cord sets and receptacles that are fixed and not exposed to damage are excepted Before each day's use Continuity test.
All equipment grounding conductors shall be electrically continuous All equipment grounding conductors Before first use Correct attachment test for the equipment grounding conductor Each receptacle and attachment cap or plug Before first use Retest Equipment returned to service following any repairs Before it goes back in service Retest Equipment after any incident which can be reasonably suspected to have caused damage Before it is used again Periodic retest Cord sets, receptacles not part of the permanent wiring, and cord- and plug-connected equipment At intervals not to exceed 3 months Periodic retest Cord sets and receptacles that are fixed and not exposed to damage At intervals not exceeding 6 months Alongside that schedule, the standard wants three things that have nothing to do with testing: A written description of the program, including the specific procedures the employer adopted, available at the jobsite for inspection and copying by the Assistant Secretary and by any affected employee.
Available at the jobsite. Not in a binder at the office. One or more designated competent persons, as defined in 1926.32(f), to implement the program. Designated, not assumed. Records of the tests. The record identifies each receptacle, cord set and cord- and plug-connected equipment that passed, with the last date tested or the interval for which it was tested.
It can be kept by logs, color coding or other effective means, and it is maintained until a more current record replaces it. That last line is why the colored tape you see wrapped around cord ends is not decoration. Quarterly color coding is one of the accepted ways to keep the record, and it is the only one a foreman can verify from six feet away.
Where it falls apart in the field The standard is not hard. Running it across a site with twelve subcontractors is. Nobody is designated. The program exists in the safety manual and no named person implements it, so the three-month clock never starts. The daily visual inspection is treated as optional.
It is the one requirement in the whole paragraph that happens every single day, and it is the one that catches a damaged cord before it matters. Borrowed tools fall out of the system. A grinder that moves between three trades belongs to whoever's program tested it last, and often that is nobody's. Damaged equipment goes back in the gang box.
The rule is plain that equipment found damaged or defective shall not be used until repaired. In practice it gets set aside, then picked up by somebody who did not see it get set aside. The record cannot be produced. Testing happened. Nobody can show which items passed or when, which under the standard is the same as not having the record.
What a GC should ask for On a multi-employer site this is worth settling before the first cord gets strung, not during an inspection. Which path is this project on, GFCI or assured grounding, and is it the same answer for every trade? If it is assured grounding, who is the designated competent person, by name, for each employer? Where does the written description live on site?
What does the current quarter's color look like, and who applies it? What happens to a cord that fails, physically, so it cannot be picked back up? A site that answers those five quickly is running the program. A site that has to go find somebody is not. Frequently Asked Questions Does a GFCI in the cord end count?
The standard requires approved ground-fault circuit interrupters for personnel protection on the covered receptacle outlets. In-line and plug-in GFCI devices are commonly used to accomplish that, but the protection has to actually be in place and working for the outlets in use, not sitting in a job box. If we use GFCIs everywhere, do we still inspect cords?
The daily visual inspection sits inside the assured grounding paragraph, so it is not triggered by the GFCI path. That said, a damaged cord is still a hazard and still citable under other parts of Subpart K, and no competent super is going to let a cord with missing pins stay in service because of which paragraph it lives in. Can different subs on the same site use different paths?
Each employer has the obligation for its own employees and equipment. That is legal and it is also how sites get confused, which is why most GCs pick one answer and write it into the subcontract. Is color coding required? No. The requirement is a record that identifies what passed and when, kept by logs, color coding or other effective means.
Color coding is just the method that survives contact with a jobsite best. What does "fixed and not exposed to damage" mean? It is the narrow exception that stretches a cord set's periodic test from three months to six, and that exempts it from the daily visual. It describes something installed and protected, not a cord that happens to be lying in a corner this week.
Key Takeaways 1926.404(b)(1) makes you choose: GFCI protection, or an assured equipment grounding conductor program. There is no third option. The GFCI path covers 120-volt, single-phase, 15- and 20-ampere receptacles that are not part of the permanent wiring and are in use by employees. The generator carve-out is narrow: two-wire, single-phase, not more than 5kW, with conductors insulated from the frame and all other grounded surfaces.
The assured grounding path requires a daily visual inspection, two tests, retests after repair or a suspected damage incident, and periodic retests at 3 months, or 6 for fixed cord sets and receptacles not exposed to damage. It also requires a written description on site, designated competent persons, and a record of what passed and when. Equipment found damaged or defective is out of service until repaired.
Related reading Electrocution is now the top killer on powered access equipment If it's not inspected, it's not safe Our electrical safety material, if you want this in a form you can hand a crew. Sources 29 CFR 1926.404, Wiring design and protection (OSHA) 29 CFR 1926.32, Definitions (OSHA) TriCore Safety is a construction and industrial safety consulting firm founded by Chris Fredette, CHST.